HELP & GUIDES

Concrete

What it's for

Figures how much concrete a pour takes: a slab, a footing, a wall, round columns or a set of formed steps. You get cubic yards, the bag count for a small pour, rebar footage or mesh sheets if you ask for them, a section drawing and a material list. It is a quantity takeoff. It does not check anything against code.

Step by step

The example is the screen as it opens: a 10' 0" by 10' 0" slab, 4" thick, 10% waste.

Concrete inputs at their defaults: POUR TYPE Slab, LENGTH 10' 0", WIDTH 10' 0", DEPTH 4", REBAR off, WELDED-WIRE MESH off, WASTE FACTOR 10%. Results read 1.36 yd³, 62 bags @ 80lb, 82 bags @ 60lb. 1 2 3 4 5
Pour type first. It decides which dimensions the screen asks for.
  1. Tap POUR TYPE and pick Slab, Footing, Wall, Column or Steps. The rows under it change to suit. The list for each type is below.
  2. Enter the dimensions. For a slab that is LENGTH and WIDTH measured inside the forms, and DEPTH, the slab thickness. Tap a value and type it in feet and inches.
  3. Turn on REBAR if you want bar footage. Two more rows appear: REBAR SIZE (#3 to #6) and REBAR SPACING, the on-center spacing of the grid. On a slab you can turn on WELDED-WIRE MESH instead, or as well. Mesh is offered for slabs only.
  4. Set WASTE FACTOR with the − and + buttons. It moves in 5% steps and is added to the concrete volume before the yards and bags are figured.
  5. Read the answer in RESULTS. On the defaults it reads 1.36 yd³, then 62 bags @ 80lb · 82 bags @ 60lb.

What each pour type asks for

Reading the results

Concrete results: 1.36 yd³, 62 bags @ 80lb, 82 bags @ 60lb, the BASIS & WHAT WAS ASSUMED row, a section drawing of a 10' 0" slab 4" thick, MATERIALS listing Concrete 1.4 yd³ and 80-lb bags (alt) 62 bags, then a dimmed SHARE PDF with a list icon at its right end, beside a lit SAVE, over the line Enter your own measurements to export. 6 9 10 11
The numbers match the list below.
  1. The headline is cubic yards, waste included. While every input is still a default the card is dimmed and tagged defaults. It clears when you change an input.
  2. Bags or truck. Up to 3 yd³ the line under the headline gives bag counts for 80 lb and 60 lb bags. Over that it reads truck territory — order ready-mix and the bag row drops out of the material list.
  3. Rebar. With REBAR on, a second line gives total feet of bar. It is bar in the pour only. The material list row says to add laps and round to stock lengths when you order. For a wall it is a single curtain of bar. For a column it is a 4-bar cage with ties at your spacing, and the row says to verify per code.
  4. BASIS & WHAT WAS ASSUMED — tap it to open. On this screen it holds the ordering advice: order in 1/4-yd steps, small loads draw short-load fees, and steps poured against fill need less than the solid figure.
  5. The drawing is a section of the pour with your dimensions on it. Pinch to zoom, double-tap to go back, and use the expand button at its top right for full screen. See Drawings.
  6. MATERIALS lists concrete to the tenth of a yard, the 80-lb bag count as an alternative, rebar in lineal feet, and mesh sheets when mesh is on.

There are no red flags on this screen. Nothing here is a pass or a fail.

The Concrete calculator is free. SHARE PDF and SAVE are part of Pro, a one-time purchase. SHARE PDF and the list icon at its right end stay dim until you have entered your own measurements, so a sheet of sample numbers never reaches a job. SAVE stays lit, but until then a tap only answers Enter your job's numbers first and saves nothing.

Common mistakes